Most shipment delays are visible three weeks before the ship date. They appear as a missed material arrival, a mould that needs another polish, or a line that has not been given a slot. A fixed weekly check turns those signals into a decision instead of a surprise.
Why weekly, not monthly
A month is long enough for a two-week slip to hide inside it. By the time a monthly report shows a problem, the recovery options — air freight, a second line, a partial shipment — have usually narrowed to the expensive ones. A weekly cadence is not diligence theatre; it is the interval at which you can still change the outcome cheaply.
The five questions, every week
Ask the same five things in the same order. Consistency is what makes week-to-week comparison possible.
- Where are the materials? Not “on the way” — arrived, in transit with a date, or not yet ordered.
- How many units are actually finished? A count, plus a photo of the finished rack.
- What is on the line this week? Which process, which station, which order.
- What is blocked? The single constraint that would stop next week’s plan.
- What changed since last week? The delta matters more than the status.
What evidence to require
Answers without evidence drift toward optimism. Three artefacts cover most of it:
- Photos with a timestamp, taken at the same angle each week — a rack that looks full from a new angle proves nothing.
- A production schedule or line card showing your order number in a slot.
- Material receipts or inbound tracking numbers for anything not yet on site.
If a supplier cannot produce these three, the constraint is usually record-keeping, not production — and that is itself worth knowing before you place the next order.
When to escalate
Escalation works best when the thresholds are set before the order, not during the argument. Three workable triggers:
- Material slip of more than one week — the whole schedule moves; ask for a revised ship date and a recovery plan in the same reply.
- Finished count below the weekly plan for two consecutive weeks — the line is not the problem; capacity or priority is.
- Same blocker reported twice — it is no longer a delay, it is a decision the factory has not made.
The record that protects you later
Keep one file per order: the weekly answers, the photos, the schedule snapshots and every ship-date revision with its date. When a delay becomes a commercial conversation — discounts, penalties, reorders — this file is the difference between a claim and an opinion.
It also makes the next order cheaper to manage: a supplier who knows you keep records tends to report earlier.
Next step
If an order is already running and you are not sure which week you are in, send the order number, the product and the current promised ship date. We will tell you what to ask for first.
See how order follow-up works or send the order details.