Order follow-up is a reporting discipline, not a friendship with the factory. Five questions, three pieces of evidence, one fixed interval — and a written record that protects you when a delay becomes a commercial conversation.
What you are buying
A weekly verified status on a running order: what is made, what is blocked, what changed, and what it means for the ship date. Not “on schedule, no problem” — a count, a photograph and a revised date where one is needed.
Where it fits
After the order is placed and before pre-shipment inspection. It is the interval where a slip can still be corrected cheaply; after the goods are packed, the only options left are expensive.
Frequency
Weekly by default. Twice weekly for a critical path, a first order with a new supplier, or a product with a long tooling lead. Monthly reporting is too slow to be useful — a two-week slip hides inside a month.
The five questions, every week
- Where are the materials? Arrived, in transit with a date, or not yet ordered.
- How many units are finished? A count, plus a photograph of the finished rack.
- What is on the line this week? Which process, which station, which order.
- What is blocked? The single active constraint.
- What changed since last week? The delta matters more than the status.
What evidence we require
Three artefacts, every week:
- Photographs with a timestamp, taken at the same angle each week. A rack that looks full from a new angle proves nothing.
- A production schedule or line card showing your order number in a slot.
- Material receipts or inbound tracking for anything not yet on site.
If a supplier cannot produce these, the constraint is usually record-keeping rather than production — which is itself worth knowing before the next order.
When we escalate
Thresholds set before the order, not during the argument:
- Material slip beyond one week — the whole schedule moves; ask for a revised ship date and a recovery plan in the same reply.
- Finished count below plan for two consecutive weeks — the line is not the problem; capacity or priority is.
- Same blocker reported twice — it is no longer a delay, it is a decision the factory has not made.
Coverage by city
Permanent in Shenzhen, Dongguan, Foshan and Guangzhou; scheduled by project in Yiwu, Ningbo, Suzhou and Shanghai. Remote follow-up works for most weeks; a site visit every four to six weeks catches what a photo cannot.
What it costs
Monthly retainer by frequency and site attendance. A weekly remote programme costs less than a twice-weekly programme with visits, and both cost less than a delayed shipment.
Price on request. Excluded: inspection fees, laboratory testing, freight, and any factory rework cost.
When the order slips
You get the slip, the cause, the recovery options and a recommendation. The commercial decision — accept, discount, air-freight, or cancel — stays with you.
Questions we get asked
Can you follow up an order we placed directly? Yes. We have no commercial relationship with the factory, which is why the reporting stays honest.
What if the factory refuses to send photos? That is a finding, and it goes in the report. Suppliers who refuse documentation usually have a reason.
Do you visit the factory? Every four to six weeks as standard, more often when the order is behind. Remote weeks are cheaper and catch most issues.
Where our responsibility ends
- We are responsible for the weekly verified status, the evidence, the escalation and the written record.
- Third parties are responsible for production itself, quality, and shipping.
- You are responsible for the commercial decision and the contract with the factory.
What you keep
Weekly report, photo set, schedule snapshots, every revised ship date with the date it changed. When a delay becomes a discount negotiation, this file is the difference between a claim and an opinion.
Next step
Send the order number, the product and the current promised ship date. We will tell you what to ask for first.