Quick read · Factory Audit
A capacity claim is easy to make and hard to disprove. Most buyers verify it by asking, which is the same as not verifying it. The signals are physical: machines, shifts, power, people and the order book.
Five signals you can see in an hour
- Machine count versus machine running — idle machines with no maintenance tag are usually not idle by choice
- Shift pattern — one shift with overtime is a different capacity from three shifts
- Power capacity — the transformer rating limits what can run at once, regardless of what is installed
- Headcount by station — a line staffed at 60% cannot hit a rate quoted for a full crew
- Order book — ask what is scheduled for the next four weeks, then ask to see the board
What “we can do 50,000 a month” usually means
It means the equipment could, on a single product, at full staffing, with material arriving on time, with no other customers. Real capacity is the number after the largest existing customer takes their share. Ask for that number directly: how much of next month is already committed.
The arithmetic that exposes a gap
Take the cycle time per unit, multiply by the number of cavities or stations, multiply by running hours, then apply a realistic efficiency figure. If the result is far below the claim, you have found the gap without arguing about it.
When a misstatement is not a lie
Some factories quote the capacity of their sister plant, or of a partner they subcontract to. That is not necessarily dishonest, but it changes who makes your goods and where. Ask which address the order will be produced at, and put it in the purchase order.
The one question that resolves it
Ask for the production schedule of the line that would run your order — machine, shift, hours, and the dates already committed to other customers. A supplier with real capacity produces a calendar in ten minutes. One without it produces an assurance.
Then compare the calendar against the quoted lead time. If the lead time assumes a line that is booked for the next six weeks, the real answer is in the calendar, not in the quotation.
Next step
Send the product, the monthly volume and the factory name. We will tell you which of the five signals can be checked remotely first.
See how factory audits are scoped or send the factory details.
Related reading
Where this guide connects
This page is one entry in a category. The service behind it is where the work actually gets done.
Send a request →