Almost every quality dispute starts with the same sentence: “the sample was fine”. It usually was. The problem is that a sample is built once, often by the most skilled person in the plant, and a production run is built many times by whoever is on the line that week.
Four things that change between sample and production
- Who builds it. An engineer-built sample and a line-built unit are different products with the same drawing.
- The tool. A sample may come from a soft tool or a CNC cut; production comes from the hardened tool. First-shot dimensions are not steady-state dimensions.
- The material batch. Colour, shrinkage and flow behaviour vary by lot. A sample made from one bag is not the same as a run made from a tonne.
- The pressure of time. Samples are not on a schedule; production is. Rushing shows up in flash, sink marks and skipped checks.
What to fix before the run starts
- A signed criteria sheet with a version number — material grade, colour standard, critical dimensions with tolerance, surface finish, assembly fit, packaging.
- A golden sample held by both sides, sealed and labelled with the same version.
- First-article inspection on the first production unit, with a full dimensional report — not a photo.
- A written rule for what happens when a dimension drifts: who is told, and within how long.
The pilot run
For a first order, a pilot of 5% to 10% of volume is the cheapest insurance available. It surfaces tool settling, material behaviour and operator learning before the whole order is exposed. If a supplier refuses a pilot, ask what they expect to go wrong.
What to inspect, and when
First-article: full dimensional report. Mid-production: critical dimensions and appearance on a sample. Pre-shipment: AQL sampling against the criteria sheet, with the golden sample present at the inspection.
The commercial point
A criteria sheet and a golden sample cost a day. A rejected container costs a month, a discount, and the relationship. The asymmetry is large enough that skipping the sheet is never a saving, even when the schedule is tight.
Next step
Send the drawing and the sample status. We will tell you which items are missing from the sheet before you approve the run.
Quality inspection · Order follow-up · Sample approval